Keller successfully delivered a design-and-build ground improvement solution using Vibro Stone Columns, enabling foundation construction within the specified programme and to the customer’s satisfaction.
The project
The substation for 132/11 kV and its facilities including GIS building, holding tank and fire pump room foundations were designed as mats. The time for completion was critical for the customer.
The challenge
Gound conditions varied across the site and with depth in terms of relative density, soil characteristics and the occurrence of problematic layers. In addition, the congested work area, with multiple contractors operating concurrently, presented challenges in maintaining smooth and uninterrupted production. Nearby overhead lines demanded strict implementation of Keller safety standards.
The solution
Keller adopted Vibro Stone Columns to meet the required bearing capacity and settlement criteria. Pre-drilling through the upper dense layers facilitated penetration of the Mono-beta vibrators for bottom-feed construction using compressed air. The works were safely completed, with zone load tests confirming the required performance prior to handover.