Ground improvement works for a major landmark retail development in Dubai were successfully delivered through proactive execution and close coordination, achieving all key milestones within the required programme.
The project
The 7.4 million square metres of residential space will include 500,000 square metres of gardens and open areas, as well as pedestrian-friendly streets. The development will also feature a technologically enhanced Ice Adventure, a rooftop waterpark, and a plaza featuring music, colour and fire.
The challenge
Highly variable ground conditions required adaptable treatment methods and increased compaction energy to achieve consistent performance across the site. The selection of a technically suitable and sufficiently productive ground improvement solution to meet the programme was an additional challenge.
The solution
Based on field trials and technical assessments, Keller optimised the treatment methodology using higher-energy Heavy Dynamic Compaction and Heavy Dynamic Replacement, significantly reducing the need for Vibro-Stone Columns. This helped meet the programme requirements while reducing material use, and the overall environmental impact.
The project recorded zero safety incidents and strong quality performance, earning client appreciation and strengthening the relationship for future collaboration.